image_print

Construction Projects

  • Contractor:  Hansen Hauling & Excavating, Inc.
  • Total Project Cost:  $1,440,492.50
  • Start Date:  May 13, 2019
  • Project Updates
    Public Information meeting is scheduled for Wednesday, February 13th at 6:30 PM. The meeting will be held in the Council Chambers of City Hall, at 500 4th Ave NE.
    April 1, 2019 – Project Awarded to Hansen Hauling & Excavating, Inc
    May 2, 2019 – Pre-construction meeting held with the contractor, Hansen Hauling & Excavating, Inc. Construction on 10th Street SW and 11th Street SW will begin on May 13, 2019.  Work on 9th Street SW is expected to begin in July.
    May 13, 2019 – The contractor is scheduled to begin removing the pavement on 10th Street SW and 11th Street SW on Thursday, May 16th. No parking will be allowed on 10th Street SW or 11th Street SW.  Please park your vehicles on an adjacent street.
    May 20, 2019 – Austin Utilities will begin water main work on 11th Street this week. The contractor finish curb removal and will begin sanitary sewer work on 10th Street this week.
    May 29, 2019 – Austin Utilities continues to work on water main on 10th St SW. Water main and service work is scheduled to be completed on 11th St SW this week.
    June 4, 2019 – Austin Utilities continues to work on water main on 10th Street SW. The contractor will begin storm sewer replacement on 11th Street SW this week.
    June 10, 2019 – The contractor will continue work on 11th Street SW this week. Austin Utilities continues to work on water main and services on 10th Street SW.

PowerPoint Presentation

  • Contractor:  Ulland Bros, Inc.
  • Total Project Cost:  $1,344,500.75
  • Start Date:  May 13, 2019
  • Project Updates
    Public Information meeting is scheduled for Wednesday, February 13th at 7:00 PM. The meeting will be held in the Council Chambers of City Hall, at 500 4th Ave NE.
    April 15, 2019 – Project Awarded to Ulland Bros, Inc.
    May 1, 2019 – Pre-construction meeting held with the contractor, Ulland Bros. Work will begin on 6th Street NW on May 13, 2019.  Work on 11th Avenue NW is expected to begin mid-June.
    May 13, 2019 – The contractor is scheduled to begin removing the pavement on 6th Street NW on Tuesday, May 14th. No parking will be allowed on 6th Street NW.  Please park your vehicles on an adjacent street.
    May 20, 2019 – Austin Utilities will begin water main and service work on 6th Street
    May 29, 2019 – Austin Utilities has completed water main installation on 6th St NW and will begin water service replacement this week. The contractor is scheduled to begin sanitary sewer and storm sewer work next week.
    June 4, 2019 – Austin Utilities will be finishing up water main and service work on 6th Street NW this week. The contractor is expected to finish removing existing curb and gutter.
    June 10, 2019 – Austin Utilities has completed water main and service work on 6th Street NW. Pavement removal will begin on 11th Avenue NW on Tuesday or Wednesday of this week.  Following pavement removal, Austin Utilities will begin water main replacement on 11th Avenue NW.  The contractor is scheduled to begin sanitary sewer and storm sewer work 6th Street NW this week.

PowerPoint Presentation

  • Contractor: Doyle Conner Co.
  • Total Project Cost:  $1,108,100.50
  • Start Date: June 10, 2019
  • Project Updates:
    Public Information meeting is scheduled for Wednesday, February 13th at 5:30 PM. The meeting will be held in the Council Chambers of City Hall, at 500 4th Ave NE.
    May 6, 2019 – Project Awarded to Doyle Conner Co.

PowerPoint Presentation

  • Contractor: Ulland Brothers, Inc.
  • Total Project Cost: $410,672.15
  • Start Date: Mid-July
  • Project Updates:
    Public Information meeting is scheduled for Wednesday, February 13th at 6:00 PM. The meeting will be held in the Council Chambers of City Hall, at 500 4th Ave NE.
    April 1, 2019 – Project Awarded to Ulland Brothers, Inc

PowerPoint Presentation

  • Contractor: Elcor Construction
  • Total Project Cost: $740,247.50
  • Start Date: May 13, 2019
  • Project Updates:
    April 15, 2019 – Project Awarded to Elcor Construction.
    May 1, 2019 – Pre-construction meeting held with the contractor, Elcor Construction. Sanitary sewer work is planned to begin on May 13, 2019.  8th Avenue NW will be closed just west of the south Riverland entrance for approximately one week.  Work in 6th Avenue NW will not take place until later in May.
    May 13, 2019 – Construction started with work on 8th Avenue NW. Work in 8th Avenue NW should last approximately one week.  The contractor may also begin manhole replacement on 6th Ave NW this week.  6th Avenue NW will be closed in the area immediately surrounding the manholes being replaced for 1-2 days.
    May 20, 2019 – The contractor has completed sanitary sewer manhole replacements on 6th Ave NW. 8th Ave NW will likely remain closed through this week, due to wet conditions.
    May 29, 2019 – The contractor is installing water main in the grass area south of 8th Ave NW. 8th Ave NW is scheduled to be reopened to traffic by the end of this week.
    June 4, 2019 – 8th Avenue NW is now open to traffic. The contractor continues to install sewer main in the open area between 6th Avenue and 8th Avenue NW.  6th Avenue NW will be closed to traffic just west of 16th Street NW by the end of the week.
    June 10, 2019 – The contractor has reached 6th Avenue NW with the sanitary sewer construction. 6th Avenue NW will be closed west of 16th Street NW for approximately 3 weeks.

5 Year Capital Improvement Plan