Construction Projects

Project Updates

PowerPoint Presentation

  • Contractor: Ulland Brothers, Inc.
  • Project Cost: $1,041,167.00
  • Start Date: Tree Removals April 25th, Construction May 2nd
  • Project Updates:

    o May 10, 2022 – Austin Utilities is working on water service replacement on 9th St & 10th St NW this week.
    o May 2, 2022 – The contractor will complete asphalt pavement removal on Monday. Curb and driveways will be removed starting on Tuesday.
    o April 28, 2022 – The contractor will be completing tree removal on Thursday and Friday of this week. Work will begin on 9th St NW and 10th St NW on Monday, May 2nd. There will be no parking allowed on the street starting at 7 AM on Monday. Please park on adjacent open streets. Vehicles in the way of construction activities may be towed.
    o April 19, 2022 – A pre-construction meeting was held to discuss the project with the contractor. Tree Removals will begin the week of April 25th. Construction work on both 9th St NW and 10th St NW will begin on May 2nd.
    o April 4, 2022 – City Council awards construction contract to Ulland Brothers, Inc.
    o March 24, 2022 – Bid opening held. Ulland Brothers Inc. was the low bidder at $1,041,167.00.
    o March 21, 2022 – Public hearing on street assessments held at the City Council Meeting.
    o February 22, 2022 – Public hearing on improvements held at the City Council Meeting.
    o February 16, 2022 – Public Information meeting held to present information about the project.

PowerPoint Presentation

  • Contractor: Ulland Brothers, Inc. 
  • Project Cost: $1,220,329.75
  • Start Date: Tree Removals – April 25
    Phase 1 (Oakland Pl NE to 1819 3rd Ave NE)– May 9th
    Phase 2 (1819 3rd Ave NE to 19th St NE) – July
  • Project Updates:
    o May 10, 2022 – The contractor milled the asphalt pavement on Monday and will continue with curb and driveway removal the rest of the week. Sanitary sewer work is expected to begin on May 16th.
    o April 28, 2022 – The contractor will be completing tree removal on Friday of this week.
    o April 19, 2022 – A pre-construction meeting was held to discuss the project with the contractor. Tree Removals will begin the week of April 25th. Construction work on Phase 1 will begin on May 9th. Work on Phase 2 will begin in July.
    o April 4, 2022 – City Council awards construction contract to Ulland Brothers, Inc.
    o March 24, 2022 – Bid opening held. Ulland Brothers Inc. was the low bidder at $1,220,329.75
    o March 21, 2022 – Public hearing on street assessments held at the City Council Meeting.
    o February 22, 2022 – Public hearing on improvements held at the City Council Meeting.
    o February 16, 2022 – Public Information meeting held to present information about the project.

PowerPoint Presentation

  • Contractor: Ulland Brothers, Inc.
  • Project Cost: $596,192.50
  • Start Date: Tree Removals April 25th, Construction May 2nd
  • Project Updates:
    o May 10, 2022 – The next step on the project is tile line and sump pump service installation. There was a material delay for the drain tile pipe. It is expected to be delivered at the end of this week with installation starting on May 16th.
    o May 2, 2022 – The contractor will complete asphalt pavement removal on Monday. Curb and driveways will be removed starting on Tuesday.
    o April 28, 2022 – The contractor will be completing tree removal on Thursday of this week. Work will begin on 3rd St NE on Monday, May 2nd. There will be no parking allowed on the street starting at 7 AM on Monday. Please park on adjacent open streets. Vehicles in the way of construction activities may be towed.
    o April 19, 2022 – A pre-construction meeting was held to discuss the project with the contractor. Tree Removals will begin the week of April 25th. Construction work will begin on May 2nd.
    o April 4, 2022 – City Council awards construction contract to Ulland Brothers, Inc.
    o March 24, 2022 – Bid opening held. Ulland Brothers Inc. was the low bidder at $596,192.50
    o March 21, 2022 – Public hearing on street assessments held at the City Council Meeting.
    o February 22, 2022 – Public hearing on improvements held at the City Council Meeting.
    o February 16, 2022 – Public Information meeting held to present information about the project.

PowerPoint Presentation

  • Contractor: To be Determined
  • Project Cost: $1,400,000.00
  • Start Date: July
  • Project Updates:
    o March 21, 2022 – Public hearing on street assessments held at the City Council Meeting.
    o February 22, 2022 – Public hearing on improvements held at the City Council Meeting.

PowerPoint Presentation

  • Contractor: Ulland Brothers
  • Project Cost: $153,576.25
  • Start Date: June 20, 2022
  • Project Updates:
    o May 10, 2022 – A preconstruction meeting was held with the contractor today. Work is expected to begin on the project around June 20th.
    o April 4, 2022 – City Council awards construction contract to Ulland Brothers, Inc.
    o March 24, 2022 – Bid opening held. Ulland Brothers Inc. was the low bidder at $153,576.25
    o March 21, 2022 – Public hearing on street assessments held at the City Council Meeting.
    o February 22, 2022 – Public hearing on improvements held at the City Council Meeting.
    o February 16, 2022 – Public Information meeting held to present information about the project.

PowerPoint Presentation

  • Contractor: Ulland Brothers
  • Project Cost: $206,862.50 
  • Start Date: June 20, 2022 
  • Project Updates:
    o May 10, 2022 – A preconstruction meeting was held with the contractor today. Work is expected to begin on the project around June 20th.
    o April 4, 2022 – City Council awards construction contract to Ulland Brothers, Inc.
    o March 24, 2022 – Bid opening held. Ulland Brothers Inc. was the low bidder at $206,862.50
    o March 21, 2022 – Public hearing on street assessments held at the City Council Meeting.
    o February 22, 2022 – Public hearing on improvements held at the City Council Meeting.
    o February 16, 2022 – Public Information meeting held to present information about the project.

PowerPoint Presentation

  • Contractor: Ulland Brothers
  • Project Cost: $159,035.00
  • Start Date: June 20, 2022
  • Project Updates:
    o May 10, 2022 – A preconstruction meeting was held with the contractor today. Work is expected to begin on the project around June 20th.

5 Year Capital Improvement Plan