image_print

Construction Projects

  • Contractor:  Hansen Hauling & Excavating, Inc.
  • Total Project Cost:  $1,440,492.50
  • Start Date:  May 13, 2019
  • Project Updates
    Public Information meeting is scheduled for Wednesday, February 13th at 6:30 PM. The meeting will be held in the Council Chambers of City Hall, at 500 4th Ave NE.
    April 1, 2019 – Project Awarded to Hansen Hauling & Excavating, Inc
    May 2, 2019 – Pre-construction meeting held with the contractor, Hansen Hauling & Excavating, Inc. Construction on 10th Street SW and 11th Street SW will begin on May 13, 2019.  Work on 9th Street SW is expected to begin in July.
    May 13, 2019 – The contractor is scheduled to begin removing the pavement on 10th Street SW and 11th Street SW on Thursday, May 16th. No parking will be allowed on 10th Street SW or 11th Street SW.  Please park your vehicles on an adjacent street.
    May 20, 2019 – Austin Utilities will begin water main work on 11th Street this week. The contractor finish curb removal and will begin sanitary sewer work on 10th Street this week.
    May 29, 2019 – Austin Utilities continues to work on water main on 10th St SW. Water main and service work is scheduled to be completed on 11th St SW this week.
    June 4, 2019 – Austin Utilities continues to work on water main on 10th Street SW. The contractor will begin storm sewer replacement on 11th Street SW this week.
    June 10, 2019 – The contractor will continue work on 11th Street SW this week. Austin Utilities continues to work on water main and services on 10th Street SW.
    June 17, 2019 – The contractor has completed the underground work on 11th Street SW and is now beginning storm sewer and sanitary sewer work on 10th Street SW. Austin Utilities has completed their work on 10th Street SW.  Pavement removal on 9th Street is planned for the end of this week.  No parking signs will be placed on the street the night before pavement removal begins.
    June 24, 2019 – The Contractor has completed storm sewer and sanitary sewer work on 10th Street SW. They will continue working on roadway excavation and tile line installation.  Austin Utilities will begin working in 9th Street SW this week.
    July 1, 2019 – The Contractor will continue working on roadway excavation and tile line installation this week on 10th Street SW. Austin Utilities will continue working on water main on 9th Street SW.
    July 9, 2019 – The Contractor plans to finish tile installation and place aggregate base this week on 10th St SW and 11th St SW. Austin Utilities continues to work on 9th St SW.
    July 15, 2019 – The Contractor will finish placing aggregate base early this this week on 10th St and 11th St SW. The next step of construction is pouring curb and gutter.  The concrete contractor is expected to begin work later this week.  Austin Utilities continues to work on water main on 9th St SW.
    July 22, 2019 – The Contractor will be pouring curb and gutter on 10th Street and 11th Street SW this week.  Austin Utilities has completed water main replacement and will now be working on water service replacement on 9th Street SW.
    July 29, 2019 – The contractor plans to continue working on curb and gutter on 10th Street and 11th Street SW. They also will be working on storm sewer on 9th Street SW.  Austin Utilities continues to replace water services on 9th Street SW.
    August 6, 2019 – The contractor will be finishing up storm sewer on 9th Street SW this week. 10th and 11th Street SW will be graded in preparation for paving.  Work on replacing driveways is scheduled to begin this week.
    August 13, 2019 – The contractor is pouring concrete driveways and sidewalk on 10th and 11th Street SW this week. Roadway excavation is taking place on 9th Street SW.
    August 19, 2019 – The contractor is planning to pave 10th Street and 11th Street SW this week. Tile is planned to be installed on 9th Street SW.

PowerPoint Presentation

  • Contractor:  Ulland Bros, Inc.
  • Total Project Cost:  $1,344,500.75
  • Start Date:  May 13, 2019
  • Project Updates
    Public Information meeting is scheduled for Wednesday, February 13th at 7:00 PM. The meeting will be held in the Council Chambers of City Hall, at 500 4th Ave NE.
    April 15, 2019 – Project Awarded to Ulland Bros, Inc.
    May 1, 2019 – Pre-construction meeting held with the contractor, Ulland Bros. Work will begin on 6th Street NW on May 13, 2019.  Work on 11th Avenue NW is expected to begin mid-June.
    May 13, 2019 – The contractor is scheduled to begin removing the pavement on 6th Street NW on Tuesday, May 14th. No parking will be allowed on 6th Street NW.  Please park your vehicles on an adjacent street.
    May 20, 2019 – Austin Utilities will begin water main and service work on 6th Street
    May 29, 2019 – Austin Utilities has completed water main installation on 6th St NW and will begin water service replacement this week. The contractor is scheduled to begin sanitary sewer and storm sewer work next week.
    June 4, 2019 – Austin Utilities will be finishing up water main and service work on 6th Street NW this week. The contractor is expected to finish removing existing curb and gutter.
    June 10, 2019 – Austin Utilities has completed water main and service work on 6th Street NW. Pavement removal will begin on 11th Avenue NW on Tuesday or Wednesday of this week.  Following pavement removal, Austin Utilities will begin water main replacement on 11th Avenue NW.  The contractor is scheduled to begin sanitary sewer and storm sewer work 6th Street NW this week.
    June 17, 2019 – Austin Utilities has started water main work on 11th Avenue NW. The contractor is expected to begin storm sewer and sanitary sewer work on 6th Street NW this week.
    June 24, 2019 – The contractor will complete sanitary sewer work this week on 6th Street NW. They will also be working on storm sewer installation.  Austin Utilities continues to work on water main on 11th Avenue NW.
    July 1, 2019 – The contractor plans to finish sanitary sewer and storm sewer work on 6th Street NW this week. After that is completed tile line installation will begin.  Austin Utilities continues to work on water main and services on 11th Avenue NW.
    July 9, 2019 – The contractor has completed storm sewer and sanitary sewer on 6th Street NW. They will begin tile installation on 6th Street NW this week.  Austin Utilities continues to work on water service replacement on 11th Avenue NW.
    July 15, 2019 – The contractor will be finishing up tile line installation and subgrade excavation on 6th St NW this week. Austin Utilities will continue to work on water service replacement on 11th Ave NW.
    July 22, 2019 – The contractor has completed tile line installation and subgrade excavation on 6th Street NW. The next step is placing aggregate base on the roadway.  Austin Utilities will be finishing up water service replacement on 11th Avenue NW this week.
    July 29, 2019 – The contractor will continue to work on placing rock on 6th Street NW and to excavate the roadway on 11th Avenue NW. Austin Utilities has completed water main and service work on the project.
    August 6, 2019 – The contractor will be working on storm and sanitary sewer on 11th Ave NW. Curb is and gutter is scheduled to begin soon on 6th Street NW.
    August 13, 2019 – The contractor will be finishing storm sewer and sanitary sewer on 11th Ave NW this week. Roadway excavation will also be taking place.
    August 19, 2019 – The contractor plans to finish curb and gutter work on 6th Street NW, and begin placing rock on 11th Avenue NW this week.

PowerPoint Presentation

  • Contractor: Doyle Conner Co.
  • Total Project Cost:  $1,108,100.50
  • Start Date: August 8, 2019
  • Project Updates:
    Public Information meeting is scheduled for Wednesday, February 13th at 5:30 PM. The meeting will be held in the Council Chambers of City Hall, at 500 4th Ave NE.
    May 6, 2019 – Project Awarded to Doyle Conner Co.
    June 24, 2019 – The contractor plans to begin work on the storm sewer outside of the roadway this week. Work on Oakland Place SE will begin after the completion of work outside the roadway, likely in two weeks.
    July 1, 2019 – The contractor will continue to work on storm sewer outside of the roadway this week.
    July 9, 2019 – The contractor continues to work on storm sewer outside of Oakland Place SE this week. Work on Oakland Place SE could begin as early as next week.
    July 15, 2019 – The contractor has completed storm sewer work outside of Oakland Place SE. We are now waiting for the CP Railroad to approve our permit before beginning work on Oakland Place SE.
    July 22, 2019 – The contractor has completed storm sewer work outside of Oakland Place SE. We are now waiting for the CP Railroad to approve our permit before beginning work on Oakland Place SE.
    July 29, 2019 – We are now waiting for the CP Railroad to approve our permit before beginning work on Oakland Place SE.
    August 2, 2019 – We have received approval from CP Railroad to begin work on the project.  Work is expected to begin on Thursday, August 8th.
    August 6, 2019 – Oakland Place SE is scheduled to close on Thursday, August 8th. Please follow detour routes.
    August 13, 2019 – The contractor continues to work on storm sewer in the 10th Street intersection. After work is completed in the 10th Street, work will begin in the 11th Street interection.
    August 19, 2019 – This week the contractor will be wrapping up storm sewer and sanitary sewer work in the 10th Street SE intersection. They will then begin underground work in the 11th Street SE intersection later in the week.

PowerPoint Presentation

  • Contractor: Ulland Brothers, Inc.
  • Total Project Cost: $410,672.15
  • Start Date: August 1, 2019
  • Project Updates:
    Public Information meeting is scheduled for Wednesday, February 13th at 6:00 PM. The meeting will be held in the Council Chambers of City Hall, at 500 4th Ave NE.
    April 1, 2019 – Project Awarded to Ulland Brothers, Inc.
    July 15, 2019 – A pre-construction meeting is scheduled for Wednesday of this week. Work is expected to begin on or around Wednesday, July 24th.  No parking signs will be placed on the street the night before work begins.  Please move all vehicles to an adjacent street.
    July 22, 2019 – The start date of the project has been delayed one week and will now be starting on or around July 31st. No parking signs will be placed on the street the night before work begins.  Please move all vehicles to an adjacent street.
    July 29, 2019 – Work on 14th Street SE will begin on Thursday morning. Please have all vehicles off of the street before 7:00 AM Thursday morning.
    August 6, 2019 – Austin Utilities will be working on replacing the water main.
    August 13, 2019 – Austin Utilities continues to work on water main replacement.
    August 19, 2019 – Austin Utilities will continue water service replacement this week.

PowerPoint Presentation

  • Contractor: Elcor Construction
  • Total Project Cost: $740,247.50
  • Start Date: May 13, 2019
  • Project Updates:
    April 15, 2019 – Project Awarded to Elcor Construction.
    May 1, 2019 – Pre-construction meeting held with the contractor, Elcor Construction. Sanitary sewer work is planned to begin on May 13, 2019.  8th Avenue NW will be closed just west of the south Riverland entrance for approximately one week.  Work in 6th Avenue NW will not take place until later in May.
    May 13, 2019 – Construction started with work on 8th Avenue NW. Work in 8th Avenue NW should last approximately one week.  The contractor may also begin manhole replacement on 6th Ave NW this week.  6th Avenue NW will be closed in the area immediately surrounding the manholes being replaced for 1-2 days.
    May 20, 2019 – The contractor has completed sanitary sewer manhole replacements on 6th Ave NW. 8th Ave NW will likely remain closed through this week, due to wet conditions.
    May 29, 2019 – The contractor is installing water main in the grass area south of 8th Ave NW. 8th Ave NW is scheduled to be reopened to traffic by the end of this week.
    June 4, 2019 – 8th Avenue NW is now open to traffic. The contractor continues to install sewer main in the open area between 6th Avenue and 8th Avenue NW.  6th Avenue NW will be closed to traffic just west of 16th Street NW by the end of the week.
    June 10, 2019 – The contractor has reached 6th Avenue NW with the sanitary sewer construction. 6th Avenue NW will be closed west of 16th Street NW for approximately 3 weeks.
    June 17, 2019 – The contractor will be completing sanitary sewer work this week. After that they will begin restoring 6th Avenue NW.
    June 24, 2019 – The contractor has completed the sanitary sewer main replacement, and all other underground work. They will begin restoring the pavement this week.
    July 1, 2019 – The contractor will continue working on restoring 6th Avenue and 8th Avenue NW this week.
    July 9, 2019 – The contractor plans to work on restoring the pavement on 6th Avenue and 8th Avenue NW this week. They would then plan on milling and overlaying the pavement on 6th Avenue NW from 14th St to 19th St next week.
    July 15, 2019 – 6th Avenue NW was milled last week and the pavement patches were paved on Saturday. The final layer of asphalt will be paved on Tuesday of this week, and the project will be complete.
    July 22, 2019 – The final layer of pavement has been placed on 6th Avenue NW and 8th Ave NW. The contractor will be on site doing some final clean up this week. The project is now complete. 

5 Year Capital Improvement Plan