image_print

Construction Projects

  • Contractor:  Doyle Conner Co.
  • Estimated Project Cost:  $1,150,775.60
  • Start Date:  10th Street NE/SE: May 4, 2020, 4th Street SW: June 15, 2020
  • Project Updates
    February 12, 2020 – Public Information meeting held to present information about the project.
    February 18, 2020 – City Council holds public hearing on street improvements.
    April 6, 2020 – Construction contract awarded by the City Council to Doyle Conner Co.
    April 28, 2020 – Work on 10th Street NE is planned to begin on Monday, May 4th. 10th Street will be closed from Oakland Place SE to 1st Avenue NE.  No parking will be allowed on 10th  Please park vehicles on an adjacent street.
    May 5, 2020 – The contractor began breaking concrete on 10th Street NE on Monday. They will begin removing the concrete on Tuesday.  Later this week, Austin Utilities will begin water main construction.
    May 11, 2020 – Concrete removal between Oakland Place SE and 1st Ave Ne was completed last week. Austin Utilities will begin water main construction today.  They will begin working at Oakland Place SE and continue north.
    May 19, 2020 – Austin Utilities will continue water main construction from 1st Avenue to 2nd Avenue NE this week.
    May 26, 2020 – Austin Utilities plans to complete water main and service construction this week. The contractor also plans to complete sanitary sewer construction this week.  After completing sanitary sewer, they will begin working on storm sewer.

Project Info Presentation

  • Contractor:  Ulland Bros, Inc.
  • Estimated Project Cost:  $1,021,063.25
  • Start Date:  July 13, 2020
  • Project Updates
    February 12, 2020 – Public Information meeting held to present information about the project.
    February 18, 2020 – City Council holds public hearing on street improvements.
    April 6, 2020 – Construction contract awarded by the City Council to Ulland Bros, Inc.
    April 28, 2020 – The contractor plans to begin tree removals on April 30th. Street reconstruction is scheduled to begin on July 13th
    May 5, 2020 – Tree removals are expected to take place this week in preparation for the street reconstruction project.
    May 11, 2020 – Tree removals will continue, and are planned to be completed this week. Street reconstruction work is scheduled to begin on July 13th.
    May 19, 2020 – Tree removals are complete. Street work is scheduled to begin on July 13th.

Project Info Presentation

  • Contractor: Ulland Bros, Inc.
  • Estimated Project Cost:  $742,136.50
  • Start Date: June 1, 2020
  • Project Updates:
    February 12, 2020 – Public Information meeting held to present information about the project.
    February 18, 2020 – City Council holds public hearing on street improvements.
    April 6, 2020 – Construction contract awarded by the City Council to Ulland Bros, Inc.
    April 28, 2020 – The contractor plans to begin tree removals on April 30th. Street reconstruction is scheduled to begin on June 1. 
    May 5, 2020 – Tree removals are expected to take place this week in preparation for the street reconstruction project.
    May 11, 2020 – Tree removals were completed last week. The project is scheduled to start on June 1st.
    May 26, 2020 – A pre-construction meeting was held today with the contractor. They plan to begin removing the existing concrete pavement on Monday, June 1st.  There will be no parking allowed on 5th Ave NE during construction.  Please park vehicles on an adjacent street.

Project Info Presentation

  • Contractor: Ulland Bros, Inc.
  • Estimated Project Cost: $1,326,455.75
  • Start Date: May 4, 2020
  • Project Updates:
    February 12, 2020 – Public Information meeting held to present information about the project.
    February 18, 2020 – City Council holds public hearing on street improvements.
    April 6, 2020 – Construction contract awarded by the City Council to Ulland Bros, Inc.
    April 28, 2020 – The contractor plans to begin tree removals on April 30th. Street reconstruction is scheduled to begin on May 4th.  There will be no parking on or access to 7th Street and 9th Avenue NW.  Please park vehicles on an adjacent street. 
    May 5, 2020 – Tree removals began on Monday and will be completed on Tuesday. Milling of the existing asphalt pavement will take place on Tuesday as well.  The contractor will then begin removing driveways and curb and gutter.  Later this week Austin Utilities will begin water main work on 7th Street NW.  The contractor will then begin sanitary sewer work on 9th Avenue NW.
    May 11, 2020 – The contractor completed tree, pavement, curb & gutter, and driveway removals last week. This week Austin Utilities will begin water main construction on 7th Street NW.
    May 19, 2020 – Austin Utilities will continue water main work on 7th Street NW and is expected to begin water main work on 9th Avenue NW later this week.
    May 26, 2020 – Austin Utilities will begin water service replacement on 7th Street and 9th Avenue NW this week.

Project Info Presentation

  • Contractor: Elcor Construction
  • Estimated Project Cost: $1,171,227.45
  • Start Date: May 18, 2020
  • Project Updates:
    April 28, 2020 – Construction is scheduled to begin on May 18th.
    May 19, 2020 – Construction will begin this week with work at the 40th Street NW and Oakland Avenue W intersection. The contractor will bore a sanitary sewer line under Oakland Avenue and begin constructing the lift station.
    May 26, 2020 – The contractor plans to continue boring sanitary sewer along and under Oakland Ave this week. The also plan to continue constructing the lift station on the south  side of Oakland Ave.  Next week they plan to begin excavation on 40th St NW.

5 Year Capital Improvement Plan