Construction Projects

PowerPoint Presentation

  • Contractor: Ulland Brothers, Inc.
  • Project Cost: $1,081,516.25
  • Start Date: 8th Street NW –May 31st, 9th Street NW – Late July
  • Project Updates:
    February 10, 2021 – Public Information meeting held to present information about the project.
    February 16, 2021 – Public hearing on proposed project held at the City Council Meeting.
    March 15, 2021 – Final public hearing held on proposed project at City Council Meeting.
    April 5, 2021 – City Council awards construction contract to Ulland Brothers, Inc.
    April 20, 2021 – A pre-construction meeting was held to discuss the project with the contractor. Work on 8th Street NW will begin on June 1st.  Work on 9th St NW will begin in late-July.

PowerPoint Presentation

  • Contractor: Doyle Conner Co.
  • Project Cost: $823,551.50
  • Start Date: May 3rd
  • Project Updates:
    February 10, 2021 –
    Public Information meeting held to present information about the project.
    February 16, 2021 – Public hearing on proposed project held at the City Council Meeting.
    March 15, 2021 – Final public hearing held on proposed project at City Council Meeting.
    April 5, 2021 – City Council awards construction contract to Doyle Conner Co.
    April 16, 2021 – A pre-construction meeting was held to discuss the project with the contractor.
    April 27, 2021 – Work on the project is scheduled to begin on Monday, May 3rd. Detour signage and temporary accesses have been constructed to parking lots. 
    May 3, 2021 – Construction has begun. The contractor will be removing concrete pavement early this week.  Austin Utilities will then begin water main construction.
    May 10, 2021 – This week Austin Utilities will be working on water main and water service installation on 1st Avenue SE.

PowerPoint Presentation

  • Contractor: Ulland Brothers, Inc.
  • Project Cost: $770,390.10
  • Start Date: 19th Street NW – May 17th, 1st Avenue NW – Early August
  • Project Updates:
    February 10, 2021 – Public Information meeting held to present information about the project.
    February 16, 2021 – Public hearing on proposed project held at the City Council Meeting.
    March 15, 2021 – Final public hearing held on proposed project at City Council Meeting.
    April 5, 2021 – City Council awards construction contract to Ulland Brothers, Inc.
    April 20, 2021 – A pre-construction meeting was held to discuss the project with the contractor. Work on 19th Street NW will begin on May 17th.  Work on 1st Ave NW will begin in early August.
    May 10, 2021 – Work on 19th Street NW is scheduled to begin on Thursday, May 20th.

PowerPoint Presentation

  • Contractor: Ulland Brothers, Inc.
  • Project Cost: $1,278,099.50
  • Start Date: 16th St NE & 1st Ave NE (from Oakland Pl NE to 16th St NE) – May 3rd, 1st Avenue NE (from 16th St to 19th St NE) – Late June
  • Project Updates:
    February 10, 2021 – Public Information meeting held to present information about the project.
    February 16, 2021 – Public hearing on proposed project held at the City Council Meeting.
    March 15, 2021 – Final public hearing held on proposed project at City Council Meeting.
    April 5, 2021 – City Council awards construction contract to Ulland Brothers, Inc.
    April 20, 2021 – A pre-construction meeting was held to discuss the project with the contractor.
    April 27, 2021 – Work on Phase 1 (16th St NE and 1600 block of 1st Ave NE) will begin on May 3rd. For the residents on Phase 1 please have all vehicles out of your driveway and street.  They can be parked on an adjacent street.  Phase 2 will begin in late June.
    May 3, 2021 – Pavement removal on 16th Street NE and the one block of 1st Avenue NE has been delayed to Wednesday, May 5th.
    May 10, 2021 – This week Austin Utilities will be working on water main and water service replacement on 16th Street NE.

PowerPoint Presentation

  • Contractor: Ulland Brothers, Inc.
  • Project Cost: Estimated $125,000.00
  • Start Date: May or June
  • Project Updates:
    February 10, 2021 – Public Information meeting held to present information about the project.
    February 16, 2021 – Public hearing on proposed project held at the City Council Meeting.
    March 15, 2021 – Final public hearing held on proposed project at City Council Meeting.
    April 19, 2021 – City Council awards construction contract to Ulland Brothers, Inc.
    May 10, 2021 – Work is scheduled to begin during the week of May 24th.

5 Year Capital Improvement Plan