Construction Projects

Project Updates

Project Info
Project Phasing & Schedule
Feasibility Report
Project Map

  • Contractor: Icon, LLC
  • Project Cost: $1,491,759.27
  • Start Date:
    • 9th Street SW – May 2, 2024
    • 12th Street SW – September 16, 2024
  • Project Updates:
    • October 21, 2024 – This week the contractor will be prepping 12th St SW for paving. Paving on 12th St is expected late this week or early next week. The contractor will also be paving 19th Ave and 22nd Ave intersections.
    • October 14, 2024 – The contractor will be completing drain tile and rock base placement on 12th St SW this week. They will also begin curb replacement.
    • October 1, 2024 – Sod and seeding is complete on 9th St SW. The remaining asphalt patches in intersections will be paved in the coming weeks. Pavement removal on 12th St SW will begin on Wednesday, October 2nd. Please remove all vehicles from the street and driveways.
    • September 18, 2024 – Next week the contractor will finish sod on 9th St and continue underground work on 12th St.
    • September 9, 2024 – The contractor plans to begin sod placement and mailbox reinstallation on 9th St on Wednesday. Sanitary sewer repairs are planned to begin on 12th St SW late this week. Full pavement removal is planned for next week on 12th St.
    • August 26, 2024 – The contractor plans to pave 9th St SW on Friday. Prior to that they will be raising manhole castings to final elevations. Late this week they will begin some sewer repairs on 12th St SW. Driveways on 12th St will remain accessible, except where work is actively taking place.
    • August 21, 2024 – The contractor hopes to pave 9th St SW late next week. They also plan to begin sewer repairs on 12th St SW next week. They do not plan to remove all the pavement on 12th St SW yet, only in the locations where they are digging for now. Those areas where digging will be painted in pink.
    • August 13, 2024 – The contractor will be working on restoring boulevards this week and final grading the rock base on 9th St SW. A date for paving is to be determined. The start of work on 12th St SW has been pushed back to late August.
    • August 7, 2024 – The contractor plans to finish grading the rock on 9th St SW. A paving date has yet to be determined.
    • July 30, 2024 – The contractor will be working on final grading of the rock on 9th St at the end of this week. Paving is expected to take place in 1-2 weeks. Work on 12th St SW is expected to begin in mid-August, an exact date is to be determined.
    • July 23, 2024 – The contractor plans to pour curb and gutter this week on 9th St. Please remove vehicles from garages and driveways. In locations where the driveway is missing, you will not be able to access your driveway until curb and driveway work has been completed.
    • July 17, 2024 – The contractor has completed storm sewer replacement and will be wrapping up drain tile installation this week.
    • July 9, 2024 – The contractor will be finishing storm sewer replacement on 9th St this week.
    • July 1, 2024 – The contractor will be working on storm sewer replacement this week.
    • June 10, 2024 – The contractor will be finishing up sanitary sewer main, and Austin Utilities will be finishing up water main work on 9th St SW this week.
    • June 3, 2024 – This week, the contractor will continue working on sanitary sewer south of 19th Ave, while Austin Utilities continues working on water services north of 19th Ave.
    • May 28, 2024 – The contractor will be working on sanitary sewer on 19th Ave this week. Austin Utilities will continue water main and service replacement on 9th St.
    • May 21, 2024 – On Thursday morning, the contractor will begin pavement removal in the 19th Ave intersection. Please make sure your vehicles are parked outside of the traffic barricades. Following pavement removal, they will be working on sanitary manhole replacement north of 19th Ave. Austin Utilities will also continue water main work north of 19th Ave. After Memorial Day weekend, the contractor will begin working on sanitary sewer south of 19th Ave.
    • May 14, 2024 – Austin Utilities will continue water main and service replacement on 9th St SW this week. Sanitary sewer work is expected to begin next week.
    • April 30, 2024 – The contractor has completed work on another street in Austin earlier than expected. They plan to move equipment to 9th St SW this afternoon and begin pavement removal. They will limit their work to one half of the street to maintain traffic. Driveways will remain accessible until Thursday. On Thursday they will begin removing the remaining pavement.
    • April 17, 2024 – A pre-construction meeting was held with the contractor, ICON. Work on 9th St SW is planned to begin on Thursday, May 2nd.
    • February 14, 2024 – Public Open House held at City Hall to present information about street reconstruction projects.
    • February 20, 2024 – Public Hearing on project improvements held at the City Council meeting.
    • March 18, 2024 – Public Hearing on Assessments was held at the City Council meeting.
    • April 1, 2024 – Bids for the project were opened on March 25th. The low bidder was ICON, LLC. The Austin City Council awarded the construction contract to ICON, LLC at the April 1st council meeting.
Project Info
Project Phasing & Schedule
Feasibility Report
Project Map

  • Contractor: Icon, LLC
  • Project Cost: $1,224,850.00
  • Start Date:
    • 2nd Ave NW (14th St to 18th St NW) – May 7, 2024
    • 2nd Ave NW (18th St to 19th St NW) – June 19, 2024
    • 16th St NW & 17th St NW – Late-August
  • Project Updates:
    • October 21, 2024 – This week the contractor will be prepping 2nd Ave & 17th St for paving. Paving is expected to take place late this week or early next week.
    • October 14, 2024 – The contractor is working on curb, sidewalks, and driveways on 17th St this week. Paving is tentatively planned for next week on 2nd Ave & 17th St.
    • October 1, 2024 – This week the contractor will be finishing up roadway excavation and drain tile installation on 17th St SW.
    • September 18, 2024 – The contractor will be finishing up driveway replacement on 2nd Ave this week. Next week they will be replacing sewer and water services on 17th St and begin placing sod on 2nd Ave.
    • September 9, 2024 – The contractor will begin sidewalk and curb replacement on 2nd Ave on Tuesday. Water main work is complete on 16th St. Sanitary Sewer work will begin on 17th St on Tuesday, followed by water main replacement late this week.
    • August 26, 2024 – The contractor plans to pave 2nd Ave NW between 14th St & 18th St on Friday. They will finish up drain tile and begin placing rock on 2nd Ave between 18th St & 19th St. Removals on 16th St NW will begin on Tuesday. Work on 17th St is planned to begin after Labor Day.
    • August 21, 2024 – The contractor will be finishing up concrete work on 2nd Ave from 14th St to 18th St this week. They are tentatively looking to pave this section of 2nd Ave late next week. Drain tile work on 2nd Ave from 18th St to 19th St will continue this week and into next. Removals on 16th St are planned to begin late next week. Work on 17th St will likely begin after Labor Day.
    • August 13, 2024 – Austin Utilities has completed all work on 2nd Ave NW. The contractor will be excavating the roadway and beginning drain tile installation between 18th St & 19th St. They will also be pouring curb and gutter between 14th St & 18th St this week. Work on 16th St & 17th St is expected to begin in a couple weeks.
    • August 7, 2024 – Austin Utilities will be finishing up water service replacement on 2nd Ave this week. The contractor will begin placing rock between 14th St & 18th St.
    • July 30, 2024 – Austin Utilities will continue working on water services on 2nd Ave between 18th St & 19th St this week. The contractor will continue installing drain tile on 2nd Ave between 14th St & 18th St. Work on 16th St & 17th St is expected to begin in mid to late August.
    • July 23, 2024 – Austin Utilities will continue working on water services on 2nd Ave between 18th St & 19th St this week. The contractor will be excavating and installing drain tile on 2nd Ave between 14th St & 18th St
    • July 17, 2024 – Austin Utilities will continue working on water services on 2nd Ave between 18th St & 19th St this week. The contractor has completed sanitary sewer MH replacement on 2nd Ave. Late this week or next week they will begin excavating the roadway.
    • July 9, 2024 – Austin Utilities will be working on water main replacement on 2nd Ave from 18th St to 19th St. The contractor plans to begin sanitary sewer manhole replacement between 14th St & 18th St late this week.
    • July 1, 2024 – Austin Utilities will be working on water main replacement on 2nd Ave NW from 18th St to 19th St.
    • June 10, 2024 – Austin Utilities will continue working on water main replacement on 2nd Ave between 14th St & 16th St this week.
    • June 3, 2024 – This week the contractor will begin removing the concrete pavement on 2nd Ave NW from 16th St to 14th St. Austin Utilities will continue with water main and service replacements.
    • May 28, 2024 – Austin Utilities will continue water service replacement on 2nd Ave NW this week.
    • May 21, 2024 – This week Austin Utilities will continue water main replacement and begin water service replacement on 2nd Ave NW.
    • May 14, 2024 – Austin Utilities will be setting up temporary water service and begin water main replacement this week
    • May 1, 2024 – Work on 2nd Ave NW between 16th St and 18th St NW is planned to begin on Monday, May 7th. Please park all vehicles on adjacent open streets.
    • April 17, 2024 – A pre-construction meeting was held with the contractor, ICON. Work on 2nd Ave NW from 16th St to 18th St NW is planned to begin on Tuesday, May 7th. They will then begin work on 2nd Ave NW between 16th St and 14th St NW later in May. Work on 2nd Ave NW from 18th St to 19th St NW will begin in June. Work on 16th St & 17th St NW will begin in August.
    • February 14, 2024 – Public Open House held at City Hall to present information about street reconstruction projects.
    • February 20, 2024 – Public Hearing on project improvements held at the City Council meeting.
    • March 18, 2024 – Public Hearing on Assessments was held at the City Council meeting.
    • April 1, 2024 – Bids for the project were opened on March 25th. The low bidder was ICON, LLC. The Austin City Council awarded the construction contract to ICON, LLC at the April 1st council meeting.
Project Info
Project Phasing & Schedule
Feasibility Report
Project Map

  • Contractor: Icon, LLC
  • Project Cost: $453,409.60
  • Start Date: April 29, 2024
  • Project Updates:
    • July 17, 2024 – Paving has been completed, boulevard restoration will begin next week.
    • July 9, 2024 – Paving is planned to be completed on 1st Ave NE late this week.
    • July 1, 2024 – The contractor will be finishing up concrete work this week.
    • June 10, 2024 – The contractor will continue roadway excavation and begin sidewalk replacement this week.
    • June 3, 2024 – The contractor expects to begin drain tile and roadway excavation this week.
    • May 28, 2024 – The contractor will begin drain tile and roadway excavation this week.
    • May 21, 2024 – The contractor will be completing storm sewer replacement this week.
    • May 14, 2024 – Austin Utilities has completed water main replacement. Storm sewer work is expected to begin at the end of the week.
    • May 1, 2024 – Work has begun on 1st Ave NE. The contractor has completed removals. Austin Utilities will now be working on water main replacement.
    • April 17, 2024 – A pre-construction meeting was held with the contractor, ICON. Work on 1st Avenue NE is planned to begin on Monday, April 29th.
    • February 14, 2024 – Public Open House held at City Hall to present information about street reconstruction projects.
    • February 20, 2024 – Public Hearing on project improvements held at the City Council meeting.
    • March 18, 2024 – Public Hearing on Assessments was held at the City Council meeting.
    • April 1, 2024 – Bids for the project were opened on March 25th. The low bidder was ICON, LLC. The Austin City Council awarded the construction contract to ICON, LLC at the April 1st council meeting.
Project Info
Project Phasing & Schedule
Feasibility Report
Project Map

  • Contractor: Icon, LLC
  • Project Cost: $829,156.20
  • Start Date:
    • 17th St NE to 1900 4th Ave NE – July 16, 2024
    • 1900 4th Ave to 19th St NE – August
  • Project Updates:
    • October 21, 2024 – Today the contractor will finish drain tile installation. They will continue placing sand and rock road base. Late this week, they will pour curb & gutter. Paving is tentatively planned for next week.
    • October 14, 2024 – Starting Tuesday, the contractor will be back on 4th Ave to work on drain tile installation. They also plan to begin placing the sand and rock road base this week.
    • October 1, 2024 – This week the contractor will be working on drain tile installation.
    • September 18, 2024 – The contractor will be working on sewer and water service replacement on phase 2 this week. They will also be finishing up roadway excavation on phase 1.
    • September 9, 2024 – The contractor completed sanitary sewer replacement this morning. Austin Utilities will begin water main replacement on Tuesday. Later this week, they will begin roadway excavation on the west end of 4th Ave.
    • August 26, 2024 – The contractor will finish removals on Phase 2. Austin Utilities will set up temporary water service the rest of this week. Sanitary sewer replacement on will begin on Tuesday after Labor Day.
    • August 21, 2024 – The contractor and Austin Utilities plan to complete sewer and water service replacement in Phase 1 this week. Pavement removal for Phase 2 is planned to begin on Monday, August 26th.
    • August 13, 2024 – The contractor and Austin Utilities will begin joint sanitary sewer and water service replacement later this week.
    • August 7, 2024 – Sanitary sewer main has been completed on Phase 1. Austin Utilities will work on water main replacement the rest of the week.
    • July 30, 2024 – The contractor will begin sanitary sewer work on 4th Ave NE on Thursday, and continue into early next week.
    • July 23, 2024 – The contractor will begin sanitary sewer work next Monday. You may drive on the street and access your driveway until sanitary sewer work begins.
    • July 17, 2024 – Work on 4th Ave NE begins today.
    • July 12, 2024 – The start date has been moved up to Tuesday, July 16th.
    • July 9, 2024 – A tentative start date for the 4th Ave NE project has been set for July 22nd.
    • July 1, 2024 – Work on the project is expected to begin in a couple of weeks.
    • June 11, 2024 – Due to weather delays on other projects, the start date for work on 4th Ave NE has been pushed back to late June or early July.
    • April 17, 2024 – A pre-construction meeting was held with the contractor, ICON. Work on 4th Ave NE is planned to begin in mid-June.
    • April 1, 2024 – Bids for the project were opened on March 25th. The low bidder was ICON, LLC. The Austin City Council awarded the construction contract to ICON, LLC at the April 1st council meeting.
Project Info
Project Phasing & Schedule
Feasibility Report
Project Map

  • Contractor: Ulland Bros, Inc.
  • Project Cost: $2,464,584.00
  • Start Date: July 15, 2024
  • Project Updates:
    • October 21, 2024 – This week water main and drain tile work will be completed on 8th St NE. The contractor will also finish placing sand and rock road base. Tuesday they will begin concrete work on the south end of 8th St. As soon as the concrete has cured, the 8th St & 16th Ave intersection will reopen to traffic, tentatively early next week.
    • October 14, 2024 – The contractor has completed all storm sewer work and will now continue with sanitary sewer installation north of 17th Ave. Austin Utilities has completed water service replacements and will also continue water main replacement to the north. Roadway excavation and placement of sand and rock base will follow behind the underground work. Concrete work is expected to begin next week.
    • October 1, 2024 – This week the contractor will continue sanitary sewer replacement north to 17th Ave. Austin Utilities will be working on water main replacement. Roadway excavation will begin on the south end of the project.
    • September 18, 2024 – The new lift station is fully operational and the contractor will continue with sanitary sewer replacement going north on 8th St NE this week.
    • September 9, 2024 – The contractor has completed sanitary sewer work between 16th Ave and I-90. This week they will start working north on 8th St and get the lift station operational.
    • August 26, 2024 – The contractor will be completing sewer work under I-90 this week. They will then begin sewer work south of 16th Ave. They will also be installing pumps and piping within the new lift station.
    • August 21, 2024 – This week the contractor will continue work on relocating fiber optic lines and setting up temporary sewer bypass pumps. They will also begin drilling sewer lines under I-90. 8th St NE is now closed from 16th Ave NE to the north.
    • August 13, 2024 – The contractor set the lift station structure last week. This week they will be backfilling and starting construction of the sanitary sewer. Closure of 8th St NE between the lift station and I-90 will take place late this week or early next week. 8th St NE between the Institute and apartments will remain open.
    • August 7, 2024 – Work continues on the lift station this week. The contractor will also continue with forcemain construction on the south side of I-90.
    • July 23, 2024 – The contractor plans to have equipment and machinery delivered to the site at the end of this week with excavation planned to begin on Monday, July 29th.
    • July 1, 2024 – Work on the project is now expected to begin the week of July 15th.
    • June 11, 2024 – The contractor plans to begin work on the project the week of June 24th.
    • May 21, 2024 – Work on the project is now expected to begin on June 5th.
    • April 30, 2024 – A pre-construction meeting was held with the contractor, Ulland Bros. Work is planned to begin on the project on May 28th.
    • April 15, 2024 – Bids for the project were opened on April 9th. The low bidder was Ulland Bros, Inc. The Austin City Council awarded the construction contract to Ulland Bros, Inc. at the April 15th council meeting.
    • February 14, 2024 – Public Open House held at City Hall to present information about street reconstruction projects.
    • February 20, 2024 – Public Hearing on project improvements held at the City Council meeting.
    • March 18, 2024 – Public Hearing on Assessments was held at the City Council meeting.
    • April 15, 2024 – Bids for the project were opened on April 9th. The low bidder was Ulland Bros, Inc. The Austin City Council awarded the construction contract to Ulland Bros, Inc. at the April 15th council meeting.

5 Year Capital Improvement Plan