Construction Projects

Project Updates

PowerPoint Presentation

  • Contractor: Ulland Brothers, Inc.
  • Project Cost: $1,041,167.00
  • Start Date: Tree Removals April 25th, Construction May 2nd
  • Project Updates:
    o July 5, 2022 – The contractor will be paving 9th St NW this week. Work on storm sewer and sanitary sewer will take place on 10th St NW this week.
    o June 28, 2022 – The contractor will be working on sidewalks, curb & gutter and driveways on 9th St NW this week. They will also continue roadway excavation and drain tile installation on 10th St NW.
    o June 21, 2022 – The contractor will begin working on replacing sidewalks on 9th St NW at the end of this week. Austin Utilities will be finishing up work on 10th St NW this week.
    o June 13, 2022 – The contractor will be finishing up drain tile this week on 9th St NW. Later in the week they will be placing rock on the road. Concrete work is expected to begin next week. On 10th St NW, Austin Utilities continues to work on water main and service replacement.
    o June 6, 2022 – The contractor will be installing drain tile and services on 9th St NW this week. Austin Utilities continues working on water main replacement on 10th St NW.
    o May 31, 2022 – Austin Utilities will continue their water main work on 10th St NW this week. The contractor plans to begin roadway excavation on 9th St NW this week, followed by drain tile installation.
    o May 24, 2022 – Austin Utilities has completed their work on 9th St NW. Next week roadway excavation and drain tile installation are expected to begin. Austin Utilities will continue work on 10th St NW this week.
    o May 19, 2022 – Austin Utilities will be finishing up water service replacement on 9th St NW this week. Austin Utilities will continue working on water main on 10th St NW this week.
    o May 10, 2022 – Austin Utilities is working on water service replacement on 9th St & 10th St NW this week.
    o May 2, 2022 – The contractor will complete asphalt pavement removal on Monday. Curb and driveways will be removed starting on Tuesday.
    o April 28, 2022 – The contractor will be completing tree removal on Thursday and Friday of this week. Work will begin on 9th St NW and 10th St NW on Monday, May 2nd. There will be no parking allowed on the street starting at 7 AM on Monday. Please park on adjacent open streets. Vehicles in the way of construction activities may be towed.
    o April 19, 2022 – A pre-construction meeting was held to discuss the project with the contractor. Tree Removals will begin the week of April 25th. Construction work on both 9th St NW and 10th St NW will begin on May 2nd.
    o April 4, 2022 – City Council awards construction contract to Ulland Brothers, Inc.
    o March 24, 2022 – Bid opening held. Ulland Brothers Inc. was the low bidder at $1,041,167.00.
    o March 21, 2022 – Public hearing on street assessments held at the City Council Meeting.
    o February 22, 2022 – Public hearing on improvements held at the City Council Meeting.
    o February 16, 2022 – Public Information meeting held to present information about the project.

PowerPoint Presentation

  • Contractor: Ulland Brothers, Inc. 
  • Project Cost: $1,220,329.75
  • Start Date: Tree Removals – April 25
    Phase 1 (Oakland Pl NE to 1819 3rd Ave NE)– May 9th
    Phase 2 (1819 3rd Ave NE to 19th St NE) – July
  • Project Updates:
    o July 5, 2022 – The contractor will be finishing up sanitary sewer work this week. Austin Utilities will be setting up temporary water service this week.
    o June 28, 2022 – The contractor will be working on sanitary sewer and manhole replacement this week. Austin Utilities will begin temporary water service installation next week.
    o June 21, 2022 – The contractor will be working on sanitary sewer and manhole replacement this week.
    o June 13, 2022 – The contractor is continuing work on sanitary sewer this week.
    o June 6, 2022 – The contractor is continuing work on sanitary sewer this week.
    o May 31, 2022 – The contractor is back and working on sanitary sewer main and service replacement this week.
    o May 24, 2022 – The contractor encountered some issues while working on the sanitary sewer. They have acquired the additional equipment needed, and plan to resume work on the sanitary sewer at the end of this week.
    o May 19, 2022 – The contractor will be working on sanitary sewer replacement on the west end of 3rd Ave NE this week.
    o May 10, 2022 – The contractor milled the asphalt pavement on Monday and will continue with curb and driveway removal the rest of the week. Sanitary sewer work is expected to begin on May 16th.
    o April 28, 2022 – The contractor will be completing tree removal on Friday of this week.
    o April 19, 2022 – A pre-construction meeting was held to discuss the project with the contractor. Tree Removals will begin the week of April 25th. Construction work on Phase 1 will begin on May 9th. Work on Phase 2 will begin in July.
    o April 4, 2022 – City Council awards construction contract to Ulland Brothers, Inc.
    o March 24, 2022 – Bid opening held. Ulland Brothers Inc. was the low bidder at $1,220,329.75
    o March 21, 2022 – Public hearing on street assessments held at the City Council Meeting.
    o February 22, 2022 – Public hearing on improvements held at the City Council Meeting.
    o February 16, 2022 – Public Information meeting held to present information about the project.

PowerPoint Presentation

  • Contractor: Ulland Brothers, Inc.
  • Project Cost: $596,192.50
  • Start Date: Tree Removals April 25th, Construction May 2nd
  • Project Updates:
    o July 5, 2022 – The contractor will be working on grading the boulevards this week.
    o June 28, 2022 – The first lift of asphalt paving was completed on Monday. The contractor plans to complete the asphalt driveways by the end of this week.
    o June 21, 2022 – The contractor will be working on asphalt driveways this week. They are planning to pave 3rd St NE on Saturday, weather permitting.
    o June 13, 2022 – Concrete curb, sidewalks and driveways have been completed. The contractor will be grading the rock and paving the road at the end of this week or early next week.
    o June 6, 2022 – The contractor is finishing up sidewalk replacement early this week. Later in the week they plan to pour concrete curb and gutter.
    o May 31, 2022 – the contractor is working on sidewalk removals early this week. Later in the week they will begin pouring the new sidewalk.
    o May 24, 2022 – The contractor has completed drain tile installation and will be placing rock on the road this week. Next, they will be removing sidewalk. Concrete work is expected to begin next week.
    o May 19, 2022 – The contractor will be finishing up drain tile construction this week.
    o May 10, 2022 – The next step on the project is tile line and sump pump service installation. There was a material delay for the drain tile pipe. It is expected to be delivered at the end of this week with installation starting on May 16th.
    o May 2, 2022 – The contractor will complete asphalt pavement removal on Monday. Curb and driveways will be removed starting on Tuesday.
    o April 28, 2022 – The contractor will be completing tree removal on Thursday of this week. Work will begin on 3rd St NE on Monday, May 2nd. There will be no parking allowed on the street starting at 7 AM on Monday. Please park on adjacent open streets. Vehicles in the way of construction activities may be towed.
    o April 19, 2022 – A pre-construction meeting was held to discuss the project with the contractor. Tree Removals will begin the week of April 25th. Construction work will begin on May 2nd.
    o April 4, 2022 – City Council awards construction contract to Ulland Brothers, Inc.
    o March 24, 2022 – Bid opening held. Ulland Brothers Inc. was the low bidder at $596,192.50
    o March 21, 2022 – Public hearing on street assessments held at the City Council Meeting.
    o February 22, 2022 – Public hearing on improvements held at the City Council Meeting.
    o February 16, 2022 – Public Information meeting held to present information about the project.

PowerPoint Presentation

  • Contractor: To be Determined
  • Project Cost: $1,400,000.00
  • Start Date: July
  • Project Updates:
    o March 21, 2022 – Public hearing on street assessments held at the City Council Meeting.
    o February 22, 2022 – Public hearing on improvements held at the City Council Meeting.

PowerPoint Presentation

  • Contractor: Ulland Brothers
  • Project Cost: $153,576.25
  • Start Date: June 20, 2022
  • Project Updates:
    o July 5, 2022 – Curb removal and replacement is planned for this week on 5th Ave SW.
    o June 28, 2022 – Milling is scheduled for Thursday of this week.
    o June 21, 2022 – Work on the project is expected to begin on June 30th, weather permitting.
    o May 10, 2022 – A preconstruction meeting was held with the contractor today. Work is expected to begin on the project around June 20th.
    o April 4, 2022 – City Council awards construction contract to Ulland Brothers, Inc.
    o March 24, 2022 – Bid opening held. Ulland Brothers Inc. was the low bidder at $153,576.25
    o March 21, 2022 – Public hearing on street assessments held at the City Council Meeting.
    o February 22, 2022 – Public hearing on improvements held at the City Council Meeting.
    o February 16, 2022 – Public Information meeting held to present information about the project.

PowerPoint Presentation

  • Contractor: Ulland Brothers
  • Project Cost: $206,862.50 
  • Start Date: June 20, 2022 
  • Project Updates:
    o July 5, 2022 – The contractor is planning on paving the second layer of asphalt this week.
    o June 28, 2022 – The contractor is paving the first lift of asphalt pavement on Tuesday.
    o June 21, 2022 – Work has begun on the project. Paving is expected to take place next week.
    o May 10, 2022 – A preconstruction meeting was held with the contractor today. Work is expected to begin on the project around June 20th.
    o April 4, 2022 – City Council awards construction contract to Ulland Brothers, Inc.
    o March 24, 2022 – Bid opening held. Ulland Brothers Inc. was the low bidder at $206,862.50
    o March 21, 2022 – Public hearing on street assessments held at the City Council Meeting.
    o February 22, 2022 – Public hearing on improvements held at the City Council Meeting.
    o February 16, 2022 – Public Information meeting held to present information about the project.

PowerPoint Presentation

  • Contractor: Ulland Brothers
  • Project Cost: $159,035.00
  • Start Date: June 20, 2022
  • Project Updates:
    o July 5, 2022 – The contractor will be working on matching in driveways this week.
    o June 28, 2022 – The first lift of asphalt pavement was paved on Monday. The second lift is planned for next week.
    o June 21, 2022 – Work is planned to begin on Thursday of this week. Paving is planned for next week.
    o May 10, 2022 – A preconstruction meeting was held with the contractor today. Work is expected to begin on the project around June 20th.

5 Year Capital Improvement Plan