Construction Projects

Project Updates

Project Info
Project Phasing & Schedule
Feasibility Report
Project Map

  • Contractor: Icon, LLC
  • Project Cost: $1,491,759.27
  • Start Date:
    • 9th Street SW – May 2, 2024
    • 12th Street SW – Mid-July
  • Project Updates:
    • July 23, 2024 – The contractor plans to pour curb and gutter this week on 9th St. Please remove vehicles from garages and driveways. In locations where the driveway is missing, you will not be able to access your driveway until curb and driveway work has been completed.
    • July 17, 2024 – The contractor has completed storm sewer replacement and will be wrapping up drain tile installation this week.
    • July 9, 2024 – The contractor will be finishing storm sewer replacement on 9th St this week.
    • July 1, 2024 – The contractor will be working on storm sewer replacement this week.
    • June 10, 2024 – The contractor will be finishing up sanitary sewer main, and Austin Utilities will be finishing up water main work on 9th St SW this week.
    • June 3, 2024 – This week, the contractor will continue working on sanitary sewer south of 19th Ave, while Austin Utilities continues working on water services north of 19th Ave.
    • May 28, 2024 – The contractor will be working on sanitary sewer on 19th Ave this week. Austin Utilities will continue water main and service replacement on 9th St.
    • May 21, 2024 – On Thursday morning, the contractor will begin pavement removal in the 19th Ave intersection. Please make sure your vehicles are parked outside of the traffic barricades. Following pavement removal, they will be working on sanitary manhole replacement north of 19th Ave. Austin Utilities will also continue water main work north of 19th Ave. After Memorial Day weekend, the contractor will begin working on sanitary sewer south of 19th Ave.
    • May 14, 2024 – Austin Utilities will continue water main and service replacement on 9th St SW this week. Sanitary sewer work is expected to begin next week.
    • April 30, 2024 – The contractor has completed work on another street in Austin earlier than expected. They plan to move equipment to 9th St SW this afternoon and begin pavement removal. They will limit their work to one half of the street to maintain traffic. Driveways will remain accessible until Thursday. On Thursday they will begin removing the remaining pavement.
    • April 17, 2024 – A pre-construction meeting was held with the contractor, ICON. Work on 9th St SW is planned to begin on Thursday, May 2nd.
    • February 14, 2024 – Public Open House held at City Hall to present information about street reconstruction projects.
    • February 20, 2024 – Public Hearing on project improvements held at the City Council meeting.
    • March 18, 2024 – Public Hearing on Assessments was held at the City Council meeting.
    • April 1, 2024 – Bids for the project were opened on March 25th. The low bidder was ICON, LLC. The Austin City Council awarded the construction contract to ICON, LLC at the April 1st council meeting.
Project Info
Project Phasing & Schedule
Feasibility Report
Project Map

  • Contractor: Icon, LLC
  • Project Cost: $1,224,850.00
  • Start Date:
    • 2nd Ave NW (14th St to 18th St NW) – May 7, 2024
    • 2nd Ave NW (18th St to 19th St NW) – June 19, 2024
    • 16th St NW & 17th St NW – Mid-August
  • Project Updates:
    • July 23, 2024 – Austin Utilities will continue working on water services on 2nd Ave between 18th St & 19th St this week. The contractor will be excavating and installing drain tile on 2nd Ave between 14th St & 18th St
    • July 17, 2024 – Austin Utilities will continue working on water services on 2nd Ave between 18th St & 19th St this week. The contractor has completed sanitary sewer MH replacement on 2nd Ave. Late this week or next week they will begin excavating the roadway.
    • July 9, 2024 – Austin Utilities will be working on water main replacement on 2nd Ave from 18th St to 19th St. The contractor plans to begin sanitary sewer manhole replacement between 14th St & 18th St late this week.
    • July 1, 2024 – Austin Utilities will be working on water main replacement on 2nd Ave NW from 18th St to 19th St.
    • June 10, 2024 – Austin Utilities will continue working on water main replacement on 2nd Ave between 14th St & 16th St this week.
    • June 3, 2024 – This week the contractor will begin removing the concrete pavement on 2nd Ave NW from 16th St to 14th St. Austin Utilities will continue with water main and service replacements.
    • May 28, 2024 – Austin Utilities will continue water service replacement on 2nd Ave NW this week.
    • May 21, 2024 – This week Austin Utilities will continue water main replacement and begin water service replacement on 2nd Ave NW.
    • May 14, 2024 – Austin Utilities will be setting up temporary water service and begin water main replacement this week
    • May 1, 2024 – Work on 2nd Ave NW between 16th St and 18th St NW is planned to begin on Monday, May 7th. Please park all vehicles on adjacent open streets.
    • April 17, 2024 – A pre-construction meeting was held with the contractor, ICON. Work on 2nd Ave NW from 16th St to 18th St NW is planned to begin on Tuesday, May 7th. They will then begin work on 2nd Ave NW between 16th St and 14th St NW later in May. Work on 2nd Ave NW from 18th St to 19th St NW will begin in June. Work on 16th St & 17th St NW will begin in August.
    • February 14, 2024 – Public Open House held at City Hall to present information about street reconstruction projects.
    • February 20, 2024 – Public Hearing on project improvements held at the City Council meeting.
    • March 18, 2024 – Public Hearing on Assessments was held at the City Council meeting.
    • April 1, 2024 – Bids for the project were opened on March 25th. The low bidder was ICON, LLC. The Austin City Council awarded the construction contract to ICON, LLC at the April 1st council meeting.
Project Info
Project Phasing & Schedule
Feasibility Report
Project Map

  • Contractor: Icon, LLC
  • Project Cost: $453,409.60
  • Start Date: April 29, 2024
  • Project Updates:
    • July 17, 2024 – Paving has been completed, boulevard restoration will begin next week.
    • July 9, 2024 – Paving is planned to be completed on 1st Ave NE late this week.
    • July 1, 2024 – The contractor will be finishing up concrete work this week.
    • June 10, 2024 – The contractor will continue roadway excavation and begin sidewalk replacement this week.
    • June 3, 2024 – The contractor expects to begin drain tile and roadway excavation this week.
    • May 28, 2024 – The contractor will begin drain tile and roadway excavation this week.
    • May 21, 2024 – The contractor will be completing storm sewer replacement this week.
    • May 14, 2024 – Austin Utilities has completed water main replacement. Storm sewer work is expected to begin at the end of the week.
    • May 1, 2024 – Work has begun on 1st Ave NE. The contractor has completed removals. Austin Utilities will now be working on water main replacement.
    • April 17, 2024 – A pre-construction meeting was held with the contractor, ICON. Work on 1st Avenue NE is planned to begin on Monday, April 29th.
    • February 14, 2024 – Public Open House held at City Hall to present information about street reconstruction projects.
    • February 20, 2024 – Public Hearing on project improvements held at the City Council meeting.
    • March 18, 2024 – Public Hearing on Assessments was held at the City Council meeting.
    • April 1, 2024 – Bids for the project were opened on March 25th. The low bidder was ICON, LLC. The Austin City Council awarded the construction contract to ICON, LLC at the April 1st council meeting.
Project Info
Project Phasing & Schedule
Feasibility Report
Project Map

  • Contractor: Icon, LLC
  • Project Cost: $829,156.20
  • Start Date:
    • 17th St NE to 1900 4th Ave NE – July 16, 2024
    • 1900 4th Ave to 19th St NE – August
  • Project Updates:
    • July 23, 2024 – The contractor will begin sanitary sewer work next Monday. You may drive on the street and access your driveway until sanitary sewer work begins.
    • July 17, 2024 – Work on 4th Ave NE begins today.
    • July 12, 2024 – The start date has been moved up to Tuesday, July 16th.
    • July 9, 2024 – A tentative start date for the 4th Ave NE project has been set for July 22nd.
    • July 1, 2024 – Work on the project is expected to begin in a couple of weeks.
    • June 11, 2024 – Due to weather delays on other projects, the start date for work on 4th Ave NE has been pushed back to late June or early July.
    • April 17, 2024 – A pre-construction meeting was held with the contractor, ICON. Work on 4th Ave NE is planned to begin in mid-June.
    • April 1, 2024 – Bids for the project were opened on March 25th. The low bidder was ICON, LLC. The Austin City Council awarded the construction contract to ICON, LLC at the April 1st council meeting.
Project Info
Project Phasing & Schedule
Feasibility Report
Project Map

  • Contractor: Ulland Bros, Inc.
  • Project Cost: $2,464,584.00
  • Start Date: July 15, 2024
  • Project Updates:
    • July 23, 2024 – The contractor plans to have equipment and machinery delivered to the site at the end of this week with excavation planned to begin on Monday, July 29th.
    • July 1, 2024 – Work on the project is now expected to begin the week of July 15th.
    • June 11, 2024 – The contractor plans to begin work on the project the week of June 24th.
    • May 21, 2024 – Work on the project is now expected to begin on June 5th.
    • April 30, 2024 – A pre-construction meeting was held with the contractor, Ulland Bros. Work is planned to begin on the project on May 28th.
    • April 15, 2024 – Bids for the project were opened on April 9th. The low bidder was Ulland Bros, Inc. The Austin City Council awarded the construction contract to Ulland Bros, Inc. at the April 15th council meeting.
    • February 14, 2024 – Public Open House held at City Hall to present information about street reconstruction projects.
    • February 20, 2024 – Public Hearing on project improvements held at the City Council meeting.
    • March 18, 2024 – Public Hearing on Assessments was held at the City Council meeting.
    • April 15, 2024 – Bids for the project were opened on April 9th. The low bidder was Ulland Bros, Inc. The Austin City Council awarded the construction contract to Ulland Bros, Inc. at the April 15th council meeting.

5 Year Capital Improvement Plan