Construction Projects

Project Updates

Project Info
Project Phasing & Schedule
Feasability Report
Project Map

  • Contractor: Icon, LLC
  • Project Cost: $1,491,759.27
  • Start Date:
    • 9th Street SW – May 2, 2024
    • 12th Street SW – Mid-July
  • Project Updates:
    • April 17, 2024 – A pre-construction meeting was held with the contractor, ICON. Work on 9th St SW is planned to begin on Thursday, May 2nd.
    • February 14, 2024 – Public Open House held at City Hall to present information about street reconstruction projects.
    • February 20, 2024 – Public Hearing on project improvements held at the City Council meeting.
    • March 18, 2024 – Public Hearing on Assessments was held at the City Council meeting.
    • April 1, 2024 – Bids for the project were opened on March 25th. The low bidder was ICON, LLC. The Austin City Council awarded the construction contract to ICON, LLC at the April 1st council meeting.
Project Info
Project Phasing & Schedule
Feasability Report
Project Map

  • Contractor: Icon, LLC
  • Project Cost: $1,224,850.00
  • Start Date:
    • 2nd Ave NW (14th St to 18th St NW) – May 7, 2024
    • 2nd Ave NW (18th St to 19th St NW) – Mid June
    • 16th St NW & 17th St NW – Mid-August
  • Project Updates:
    • April 17, 2024 – A pre-construction meeting was held with the contractor, ICON. Work on 2nd Ave NW from 16th St to 18th St NW is planned to begin on Tuesday, May 7th. They will then begin work on 2nd Ave NW between 16th St and 14th St NW later in May. Work on 2nd Ave NW from 18th St to 19th St NW will begin in June. Work on 16th St & 17th St NW will begin in August.
    • February 14, 2024 – Public Open House held at City Hall to present information about street reconstruction projects.
    • February 20, 2024 – Public Hearing on project improvements held at the City Council meeting.
    • March 18, 2024 – Public Hearing on Assessments was held at the City Council meeting.
    • April 1, 2024 – Bids for the project were opened on March 25th. The low bidder was ICON, LLC. The Austin City Council awarded the construction contract to ICON, LLC at the April 1st council meeting.
Project Info
Project Phasing & Schedule
Feasability Report
Project Map

  • Contractor: Icon, LLC
  • Project Cost: $453,409.60
  • Start Date: April 29, 2024
  • Project Updates:
    • April 17, 2024 – A pre-construction meeting was held with the contractor, ICON. Work on 1st Avenue NE is planned to begin on Monday, April 29th.
    • February 14, 2024 – Public Open House held at City Hall to present information about street reconstruction projects.
    • February 20, 2024 – Public Hearing on project improvements held at the City Council meeting.
    • March 18, 2024 – Public Hearing on Assessments was held at the City Council meeting.
    • April 1, 2024 – Bids for the project were opened on March 25th. The low bidder was ICON, LLC. The Austin City Council awarded the construction contract to ICON, LLC at the April 1st council meeting.
Project Info
Project Phasing & Schedule
Feasability Report
Project Map

  • Contractor: Icon, LLC
  • Project Cost: $829,156.20
  • Start Date:
    • 17th St NE to 1900 4th Ave NE – Mid June
    • 1900 4th Ave to 19th St NE – Mid July
  • Project Updates:
    • April 17, 2024 – A pre-construction meeting was held with the contractor, ICON. Work on 4th Ave NE is planned to begin in mid-June.
    • February 14, 2024 – Public Open House held at City Hall to present information about street reconstruction projects.
    • February 20, 2024 – Public Hearing on project improvements held at the City Council meeting.
    • March 18, 2024 – Public Hearing on Assessments was held at the City Council meeting.
    • April 1, 2024 – Bids for the project were opened on March 25th. The low bidder was ICON, LLC. The Austin City Council awarded the construction contract to ICON, LLC at the April 1st council meeting.
Project Info
Project Phasing & Schedule
Feasability Report
Project Map

  • Contractor: Ulland Bros, Inc.
  • Project Cost: $2,464,584.00
  • Start Date: May 2024
  • Project Updates:
    • April 15, 2024 – Bids for the project were opened on April 9th. The low bidder was Ulland Bros, Inc. The Austin City Council awarded the construction contract to Ulland Bros, Inc. at the April 15th council meeting.
    • February 14, 2024 – Public Open House held at City Hall to present information about street reconstruction projects.
    • February 20, 2024 – Public Hearing on project improvements held at the City Council meeting.
    • March 18, 2024 – Public Hearing on Assessments was held at the City Council meeting.
    • April 15, 2024 – Bids for the project were opened on April 9th. The low bidder was Ulland Bros, Inc. The Austin City Council awarded the construction contract to Ulland Bros, Inc. at the April 15th council meeting.

5 Year Capital Improvement Plan